How to Build Floor-to-Ceiling Shelves
click on image to enlarge

1. Mark the location for two parallel 2 × 4 top plates on the ceiling, using a framing square as a guide. The front edge of the outer top plate should be 13" from back wall, and the other top plate should be flush against the wall. Mark location of ceiling joists; if necessary, install blocking between joists to provide a surface for anchoring the top plates.

click on image to enlarge

2. Measure and cut 2 × 4 top plates. Position each plate, check to make sure it is level, and shim if necessary. Attach plates to ceiling with 3" screws driven into the joists or blocking.

click on image to enlarge

3. Cut 2 × 4 sole plates and screw them together to form two doubled sole plates. Use a plumb bob suspended from the outside corners of the top plates to align the sole plates, then shim to level, if needed; anchor the plates by driving 3" screws toenail-style into the floor.

click on image to enlarge

4. Install 2 × 4 support studs between the ends of the top plates and sole plates. Attach support studs with 3" screws driven toenail-style into the top plates and sole plates.

click on image to enlarge

5. Install center support studs midway between the end support studs. Attach to bottom plate first, using 3" screws driven toenail-style. Use a level to make sure that stud is plumb, then attach the studs to the top plate with 3" screws.

click on image to enlarge

6. Where the shelves fit into a corner, use 2" screws to attach 1/2" plywood spacers on the inside faces of the support studs, spaced every 4". Make sure spacers do not extend past the front face of the studs.

click on image to enlarge

7. Where the end of the project is exposed, measure and cut a 1/2" plywood end panel to floor-to-ceiling height. Attach the panel to the support studs so the front edges are flush, using 1 3/4" screws driven through the support studs and into the end panel.

click on image to enlarge

8. Measure and cut 1/2" plywood top and bottom panels to fit between the support studs. Attach to the top and sole plates using 1 1/2" finish nails.

click on image to enlarge

9. Measure and cut lower risers from 1/2" plywood, then cut dadoes for metal shelf standards.

click on image to enlarge

10. Install lower risers on each side of the 2 × 4 support studs so the front edges are flush with the edges of the studs. Attach risers with 1 1/2" finish nails driven into the support stud. For riser that adjoins wall, drive nails at spacer locations.

click on image to enlarge

11. Measure and cut permanent shelves from 3/4" plywood to fit between the support studs, just above the lower risers. Set shelves on risers and attach them with 1 1/2" finish nails driven down into the risers.

click on image to enlarge

12. Measure and cut upper risers to fit between permanent shelves and the top panels. Cut dadoes for metal shelf standards, then attach the risers to the support studs with 1 1/2" finish nails.

click on image to enlarge

13. Measure and cut 1 × 3 stiles to reach from floor to ceiling along the front edges of the exposed support studs. Drill pilot holes and attach the stiles to the support studs so they are flush with the risers, using glue and 1 1/2" finish nails driven at 8" intervals into the studs and risers.

click on image to enlarge

14. Measure and cut 1 × 3 top rails to fit between stiles. Drill pilot holes and attach the rails to the top plate and top panels, using glue and 1 1/2" finish nails.

click on image to enlarge

15. Measure and cut 1 × 4 bottom rails to fit between the stiles. Drill pilot holes, and attach the rails to the sole plates and bottom panels, using glue and 1 1/2" finish nails. The top edge of the rails should be flush with the top surface of the plywood panels.

click on image to enlarge

16. Fill nail holes, then sand and finish the wood surfaces.

click on image to enlarge

17. Measure, cut, and install metal shelf standards into the dadoes using nails or screws provided by the manufacturer.

click on image to enlarge

18. Measure and cut adjustable 1/8" shorter than the distance between metal standards. Cut shelf edging, and attach with glue and 1 1/2" finish nails. Sand and finish the shelves.

click on image to enlarge

19. Insert shelf clips into metal shelf standards and install the adjustable shelves at desired heights.

click on image to enlarge

20. Cover gaps between the project and walls and floor with molding that has been finished to match the shelf unit.

 
Next Steps and Related Projects:
 
 How to Build Floor-to-Ceiling Shelves
 
Return to TopReturn To Top
Print-FriendlyPrint-Friendly Version
 
RELATED PRODUCTS
AutoTape™ 25' Powered Tape Measure
AutoTape™ 25' Powered Tape Measure
 

7-1/4" 13 Amp Circular Saw
7-1/4" 13 Amp Circular Saw
 

6.0 Amp VSR 1/2" Drill / Driver
6.0 Amp VSR 1/2" Drill / Driver
 

Help Center: Important Safety Recalls/Notices Traveling Safely with Batteries and Battery Powered Devices
Where To Buy | Instant Answers | Email Customer Service | Product Ideas | Privacy Policy | Recalls
Service Center Locator | Factory Stores | Warranty
Power Tools |  Energy |  Hand Tools |  Outdoor |  Cleaning |  Automotive |  Portable Power |  Home Appliances
Repair Books |  Shredders |  Storage |  Personal Protective Equipment |  Product Guide
Black and Decker is the world's largest manufacturer of power tools & accessories.

© Copyright 2009, Black & Decker. 
All rights reserved.

Company Information | Careers | Investor Relations | Citizenship